DESIGN
INFORMATION FOR POLYFORM POLYSLABS - COPYRIGHT RESERVED
This
information is based on SABS 0100-1: 2000 and is intended to serve as a guide
only for the professional engineer responsible for the structural design of the
project.
Polyform PolySlab
systems comprise interlocking polystyrene blocks and ribs which form a
permanent shutter into which reinforcing and concrete are placed.
DESIGN
GRAPHS
The graphs are based on the
ultimate moments provided by the relative reinforcement indicated at the bottom
of the ribs. The nominal dead loads are factored by 1.2 and the imposed loads
by 1.6. A nominal load of 0.66 KPa for 30mm floor screed has been allowed, in
addition to the self weight. As no plaster is required for the ceilings,
additional load must be allowed where suspended ceilings are specified.
The graphs are for simply
supported spans with uniformly distributed nominal imposed loads. Localised concentrated loads (see Table 4 SABS
0160 - 1989) or line loads from partitions can
be distributed as per SABS 0100 clause 6.2.2.2. The effects of these on shear
have to be checked. The thicker lines shown on the graphs
allow for the deflection limitations described in SABS 0100-1: 2000 Clause
4.3.6 for span/depth ratio of approximately 20. The thinner line can be used at
the Engineers discretion where deflections are not crucial. Where slab supports partitions, the deflection
must be limited as in clause 3.2.3.2.1.2
Allow for minimum
reinforcement over continuous supports specified in clause 4.5.6.2.1 .
Additional
reinforcing to the mesh may be required.
The graphs allow for 15mm
cover to the bottom reinforcement, 60mm structural concrete topping and 30mm
screed which provides for 0.5 hours fire resistance [Table 45 e)]and mild
exposure conditions for 25MPa concrete. Alternatively a 90mm
structural concrete topping, without screed, can be used.
VERTICAL SHEAR
The point at which
shear exceeds the permissible value of `vc’ in the code, assuming all bars are
taken through to the supports, is indicated by grey ellipse on the graphs. In the case where only one bar is taken
through to the support and the other bar is curtailed the critical shear point
on the graph is indicated by a boxed "1". Where this point is not
shown on the graph, the Engineer should check shear manually if bars are to be
curtailed. Where `v’ exceeds `vc’ shear
reinforcement will be required [clause 4.5.4].
The punching shear
for concentrated load specified by SABS 0160 -1989 and spread according to
Clause 4.4.5.2.3 of SABS 0100 - 2000 must be checked.
REINFORCING IN TOPPING
Minimum reinforcing
in a 60mm thick topping, according to Clause 4.5.6.2.2 is weld mesh Ref. 156 (99mm2/m)
or equivalent in reinforcing bars.
TEMPORARY SUPPORT LINES FOR POLYSTYRENE FORMWORK
Temporary support spacings should
allow for a nominal construction line load of 2 KN/m over a 300 mm width
transverse to ribs [taken from composite beams in SA Steel Construction
Handbook] in addition to the appropriate dead load. The maximum
spacing of supports is determined by the strength of the polystyrene blocks
and acceptable self weight deflections[calculation spread sheet available]. A factor
of safety of 2.5 is recommended. Normally blocks are specified of 16 Kg/cum
polystyrene [ultimate flexural strength = 160 KPa] up to 170 mm thick & `X’
grade[ ultimate flexural strength = 80 KPa] above.
DRAWINGS
Besides the
reinforced concrete details, the drawings or separate overlays should indicate
the marked Polyform products and the temporary supports. Polyform
product order sheets are provided, to be completed by the Engineer. The order will be processed by the Polyform
Agent.
CONSTRUCTION PROCEDURES
The relevant Polyform
Erection forms ERS + erection drawing PE for Polyslabs, ERT for Poly T Slabs
and ERST for stairs must form part of
the documents issued. The Contractor's attention
must be drawn to provisions required for windy conditions.
|